An application for a building permit shall be considered abandoned and void, and the plan review fee will not be refunded, if:
(A) One hundred-eighty days has passed since the date that the applicant was notified that the permit was ready for pickup and the permit has not been picked up; or
(B) One hundred-eighty days has passed since the permit application was submitted and the applicant has not responded to the building inspector's request(s) for modifications or additional information so as to allow final processing and issuance of the permit.
(Ord. passed 9-18-2018)