(a) The developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM site plan for activities involving proposed impervious surfaces 1,000 square feet or greater and for earth disturbances 5,000 square feet or greater. The as-built plans and all explanation of any discrepancies with the construction plans shall be submitted to the municipality within three months of the completion of construction of the SWM BMPs.
(b) As-built plans shall show the location and as-built conditions of all SWM BMP structures and include the following information: impervious surfaces included in the approved SWM site plan; topographic contours; and existing, proposed and built impervious surfaces shown in the as-built drawings.
(c) The as-built submission shall include a certification of completion signed by a design professional verifying that all permanent SWM BMPs have been constructed according to the approved plans and specifications.
(d) The municipality will review the as-built submission for consistency with the approved SWM site plan as well as actual conditions at the project site. After receipt of the completion certification by the municipality, the municipality may conduct a final inspection.
(Ord. 928, passed 6-18-2014)