(a) The Municipal Engineer or his or her municipal designee shall inspect all phases of the installation of the permanent BMPs and/or stormwater management facilities as deemed appropriate by the Municipal Engineer.
(b) During any stage of the work, if the Municipal Engineer or his or her municipal designee determines that the permanent BMPs and/or stormwater management facilities are not being installed in accordance with the approved stormwater management plan, the municipality may revoke any existing permits or other approvals and issue a cease and desist order until a revised SWM site plan is submitted and approved, as specified in this chapter, and until the deficiencies are corrected.
(c) A final inspection of all BMPs and/or stormwater management facilities shall be conducted by the Municipal Engineer or his or her municipal designee to confirm compliance with the approved SWM site plan prior to the issuance of any occupancy permit.
(Ord. 928, passed 6-18-2014)