§ 53.103  STORMWATER PLAN MODIFICATIONS.
   (A)   If the request for a plan modification is initiated before construction begins, the stormwater plan must be resubmitted and reviewed according to the procedures contained in § 53.101.
   (B)   If the request for a plan modification is initiated after construction is underway, the Municipal Engineer shall recommend approval or disapproval of the modification based on field inspection provided:
      (1)   The requested changes in stormwater controls do not result in any modifications to other approved municipal land use/development requirements (e.g., building setbacks, yards and the like); and
      (2)   The performance standards in §§ 53.025 and 53.026 and §§ 53.040 through 53.042 are met.
   (C)   Notification of the engineer’s action shall be sent to the governing body which may issue a stay of the plan modification within 14 days and require the permittee to resubmit the plan modification for full stormwater plan review in accordance with § 53.101.
(Ord. 4-2011, passed 10-8-2011)