(A) Documentation.
(1) No permit or approvals related to the project site shall be issued by the city until the applicant complies with the provisions of this section. The completed WMP must be approved prior to final occupancy. A temporary occupancy may be granted by the Building Official.
(2) The applicant shall submit documentation along with a completed WMP that documents the diversion requirement for the project has been met to the City Compliance Official in order to receive final occupancy approval. This documentation shall include the following:
(a) The completed WMP submitted for approval shall list for each construction and demolition material type generated the actual material volume or weight the project generated and receipts from both the disposal and recycling facilities and/or licensed haulers and vendors that received each material showing clearly whether the material was disposed or recycled; and
(b) Any additional information the applicant believes is relevant to determining its efforts to comply in good faith with this article.
(B) Weighing of wastes. Applicants shall make reasonable efforts to ensure that all C&D debris diverted or landfilled are measured and recorded using the most accurate method of measurement available. To the extent practical, all construction and demolition debris shall be weighed by measurement on scales. Such scales shall be in compliance with all regulatory requirements for accuracy and maintenance. For construction and demolition debris for which weighing is not practical due to small size or other considerations, a volumetric measurement shall be used.
(C) Determination of compliance and release of permit. The WMP Compliance Official shall review the information submitted under division (A) above and determine whether the applicant has complied with the diversion requirement, as follows:
(1) Full compliance. If the WMP Compliance Officer determines that the applicant has fully complied with the diversion requirement applicable to the project, he or she shall indicate such compliance on the WMP.
(2) Good faith effort to comply. If the WMP Compliance Official determines that the diversion requirement has not been achieved, he or she shall determine on a case-by-case basis whether the applicant has made a good faith effort to comply with this article. In making this determination, the WMP Compliance Official shall consider the availability of markets for the C&D debris landfilled, the size of the project, and the documented efforts of the applicant to divert C&D debris. If the WMP Compliance Official determines that the applicant has made a good faith effort to comply with this article, he or she shall so indicate on the WMP.
(3) Noncompliance. If the WMP Compliance Official determines that the applicant has not made a good faith effort to comply with this article, or if the applicant fails to submit the documentation required by division (A) above within the required time period, then the applicant shall be in violation of this article and be liable for a civil penalty, including that authorized by § 9-5.2707.1 of this code, in addition to any other remedy provided by this article.
(Ord. 2123-C-S, passed 1-10-17; Am. Ord. 2200-C-S, passed 1-11-22)