A. Every principal use and every lot within a subdivision shall have available to it a source of electric power adequate to accommodate the reasonable needs of the use and every lot within the subdivision. Compliance with this requirement shall be determined as follows:
B. If the use is not a subdivision and is located on a lot that is served by an existing power line and the use can be served by a simple connection to the power line, then no further certification is needed; and
C. If the use is a subdivision or is not located on a lot served by an existing power line or a substantial internal distribution system will be necessary, then the electric utility service provider must review the proposed plans and certify to the Town that it can provide service that is adequate to meet the needs of the proposed use and every lot within the proposed subdivision.
(Ord. 2020-36, passed 12-2-2019)