9.63.110: EXTENSION OF TIME:
The commission may grant a time extension not to exceed three (3) years. Applications shall be made on a form to be provided by the planning division. Prior to the granting of an extension, the planning division shall review the previously approved project to ensure it is consistent with all current provisions of the general plan, development code and other town ordinances and that the findings for approval of a conditional use permit in compliance with section 9.63.080, "Required Findings", of this chapter, can be made. Based upon this review, additional conditions of approval may be imposed upon the project by the review authority when the extension of time is approved.
The commission may grant additional extensions of time provided that the project is consistent with the general plan, development code, master plans and specific plans. (Ord. 243, 10-15-2013)