(A) Generally.
(1) Within 24 working hours of commencement of the installation of the geothermal system, it shall be the duty of the permit holder to notify the City Engineer, who shall instruct the inspector to inspect, from time to time for the duration of the work, the installation.
(2) Upon completion, if it is found to be fully in compliance with this chapter and does not constitute a hazard to life and property, the inspector shall issue to the permit holder, a certificate of inspection authorizing connection to the geothermal system.
(Prior Code, § 9.1-29)
(B) Right of inspection authority to require contractor’s representative to be present. The inspection authority reserves the right to require a representative of the approved person or contractor to be on the job when inspection is made.
(Prior Code, § 9.1-30)
(Ord. 1337, passed 11-22-2010)