1123.15 SANITARY SEWERS AND SEWAGE DISPOSAL FACILITIES.
   (a)   The subdivider shall install all necessary sewer mains, street mains and lateral connections completed to the front line of each lot within the subdivision, including all necessary man holes, required sumps or pumping stations.
 
   (b)   All sanitary sewer mains are to be no less than nine feet below grade or shall be no less than two feet lower than any basement to be served, whichever is greater. All service lines shall be a minimum of three feet deep and/or one foot lower than the basement or house line and extend to a gradual fall off the main.
 
   (c)   All plans for said sewer and water lines shall be presented and approved by the Village Administrator prior to work commencing on the same.
(Ord. 1972-31. Passed 10-3-72.)