Section 15.54.070   Construction and demolition debris diversion requirements.
   A.   Diversion from Landfill Waste Required. Construction and demolition debris shall be diverted from the landfill waste stream for recycling at the rates, measured by weight, set forth in the following subsections B and C.
   B.   Initial Diversion Requirements. For all covered projects for which a building or demolition permit application is submitted on or after January 1, 2011, at least fifty percent (50%) of construction and demolition debris shall be recycled in accordance with a waste reduction and recycling plan that complies with Section 15.54.080 of this chapter.
   C.   Subsequent Diversion Requirements. For all covered projects for which a building or demolition permit application is submitted on or after January 1, 2012, at least seventy-five percent (75%) of construction and demolition debris shall be recycled in accordance with a waste reduction and recycling plan that complies with Section 15.54.080 of this chapter.
(MC-5-2010, § 2, 10/19/2010)