Section 15.52.080   Issuance of demolition permit.
   A.   Except as provided in the following subsection (B), a demolition permit shall be approved and issued in the following circumstances:
      1.   If the Historic Preservation Commission determines that an historic and architectural impact study is not warranted;
      2.   If the Historic Preservation Commission determines, upon the completion of an historic and architectural impact study, that a delay to seek alternatives to demolition is not warranted; and
      3.   If any delay authorized by subsections (a) or (D) of Section 15.52.070 has expired.
   B.   No demolition permit shall be issued if any of the following circumstances exists:
      1.   If a delay imposed by the Director of Public Works pursuant to Section 15.52.070(B) is in effect;
      2.   If a delay imposed by the Village Manager pursuant to Section 15.52.070(C) is in effect;
      3.   If a delay authorized by subsection (A) or (D) remains in effect;
      4.   If a complete application for a building permit has not been submitted; and
      5.   If the applicant has failed to file a waste reduction and recycling plan as required by Section 15.54.080 of this Code, or, if a demolition and recycling plan filed by an applicant fails to meet the requirements for approval as provided in Chapter 15.54 of this Code.
(MC-06-2024, Amended, 7/16/2024; MC-5-2010, § 6, Amended 10/19/2010; MC-5-2009, Amended, 05/05/2009; MC-7-2001, Amended, 08-21-2001)