Section 15.32.090   Approval and issuance of permit.
   A.   Issuance; Payment of Fees. Upon approval of a permit application, the permit shall be issued by the Director to the owner only if all required fees and costs then due from or owed by the owner or any contractor have been paid. No permit shall be in force or effect until it has been issued pursuant to this section.
   B.   Approval Stamps. When the building official issues a permit, the building official shall indicate approval of construction documents in writing or by stamp, as "Approved/Approved as Noted." Stamps or written notes of approval shall be shown on at least two sets of the approved construction documents for all aspects of the permit work subject to specific code compliance, depending on the scope of the work, including, but not limited to, building, engineering, fire prevention, forestry, HVAC, mechanical, health and sanitation, electrical and plumbing codes, and the Zoning Ordinance.
(Prior code § 23.17)
   C.   Delay for Public Convenience and Safety. The Director of Public Works may order that the issuance of a permit be delayed if the proposed schedule for the construction activity will interfere with previously scheduled works in the public rights-of-way in the immediate vicinity of the subject property, or if the Director of Public Works determines that delay is necessary to prevent undue congestion and noise impacts in the neighborhoods when the traffic or noise from the proposed demolition combined with traffic or noise from previously scheduled public works projects in the immediate neighborhood.
   D.   Administrative Delay. The Director may delay the issuance of a permit for a new primary structure for up to sixty (60) days if one or more building or demolition permits for primary structures have been approved for properties, for which work is continuing, on either side of the right-of-way block face and/or alley along which the property is located, or if the Director determines that a delay is necessary to prevent undue congestion and noise impacts in the neighborhood.
(Amended MC-10-2002, 11/19/02)
(MC-3-2005, Amended, 06/21/2005; MC-10-2002, Amended, 11/19/2002)