(A) Fee zones. The following are building permit fees, zoning fees, and inspection fees for districts AG, R-1, R-2, R-3, R-4, MF, and PDR.
(B) Residential building permit fees.
Residential Building Permit Fees for New Construction and Remodeling, Based on Floor Space
| ||
Type of Dwelling | Type of Construction | Fees |
Residential Building Permit Fees for New Construction and Remodeling, Based on Floor Space
| ||
Type of Dwelling | Type of Construction | Fees |
Multi-family and condominiums | Basements, single-family access and use only | $0.65 per sq. ft. |
Multi-family and condominiums | Garages, attached and unattached | $0.43 per sq. ft. |
Multi-family and condominiums | Living areas and common areas | $0.70 per sq. ft. |
Multi-family and condominiums | Crawl space | $0.43 per sq. ft. |
One- and two-family dwellings | Basements | $0.54 per sq. ft. |
One- and two-family dwellings | Garages, attached and unattached | $0.38 per sq. ft. |
One- and two-family dwellings | Living space | $0.70 per sq. ft. |
One- and two-family dwellings | Crawl space | $0.43 per sq. ft. |
(C) Accessory building or structure permit fees.
Residential Accessory Building or Structure Permit Fees for New Construction and Remodeling, Based on Floor Space | ||
Type of Structure | Type of Construction | Fees |
Residential Accessory Building or Structure Permit Fees for New Construction and Remodeling, Based on Floor Space | ||
Type of Structure | Type of Construction | Fees |
Buildings and structures used in direct production of agricultural commodities and livestock, and related equipment storage | $0.35 per sq. ft. | |
Communication towers and antennas | Satellite dishes over 24 inches in diameter | $35 each |
Communication towers and antennas | Standalone towers and antennas | $5 per ft. in height |
Communication towers and antennas | Roof- or wall-mounted towers and antennas | $25 each |
Communication towers and antennas | Engineering fees if required | Paid by permit holder |
Construction trailers | $350 each | |
Multi-family and condominiums | Decks, porches, patios, storage buildings | $0.25 per sq. ft. |
One- and two-family structures | Decks, porches, patios, storage buildings | $0.25 per sq. ft. |
Swimming pools | Above ground up to 30 feet in diameter | $55 each |
Swimming pools | Each additional foot over 30 or fraction thereof | $0.15 per ft. |
Swimming pools | In ground up to 800 square feet (20 × 40) | $100 each |
Swimming pools | Each additional sq. ft. over 800 or fraction thereof | $0.15 per sq. ft. |
(D) Certificate of occupancy fees.
Certificate of Occupancy Fees for New Residential Construction and Remodeling | ||
Type of Structure | Type of Dwelling | Fees |
Accessory buildings, if required | Multi-family and condominiums | $25 each structure |
Accessory buildings, if required | One- and two-family structures, agricultural | $30 each structure |
Residences | Multi-family and condominiums | $60 each unit |
Residences | One- and two-family structures | $40 each unit |
(E) Zoning fees.
Zoning Fees, Residential | |||
Type of Structure | Type of Construction | Type of Dwelling | Fees |
Zoning Fees, Residential | |||
Type of Structure | Type of Construction | Type of Dwelling | Fees |
Accessory structures | New construction and demolition | One- and two-family, agricultural | $35 each structure |
Accessory structures | New construction and demolition | Multi-family and condominiums | $35 each structure |
Dwelling units | New construction | One- and two-family structures | $135 each structure |
Dwelling units | New construction | Multi-family and condominiums | $235 each structure |
Dwelling units | Additions, remodeling, and demolition | Single-family structures | $140 each structure |
Dwelling units | Additions, remodeling, and demolition | Multi-family and condominiums | $50 each structure |
(F) Other construction permit fees.
Other Residential Construction Permit Fees | ||
Type of Permit | Comments | Fees |
Other Residential Construction Permit Fees | ||
Type of Permit | Comments | Fees |
Fence permit | Not allowed in easements without affidavit release Includes zoning fee–all zones | $75 per fence |
Foundation-only permit; optional | Details in division (L) of this section | $250 administrative, plus $.50 per sq. ft. of area covered by the foundation |
Replacement permit cards | $25 each | |
Sign permit | Non-exempt, includes zoning fee | $35 per sign |
Sign permit–Real estate | Non-exempt, includes zoning fee, 4 sq. ft. | $35 per sign |
Site development | $150 per property | |
Utility service change or upgrade–permit and inspection | Gas, electric, sewer, septic, private well, or community water system | $120 each service change |
(G) Inspection fees.
Inspection Fees, Residential | |||
Type of Inspection | Item | Item Details | Fees |
Inspection Fees, Residential | |||
Type of Inspection | Item | Item Details | Fees |
Amended permit fee | At anytime a permit needs to be amended, plus costs (i.e., inspections, square footage, and the like) | $50 | |
Concrete floors or walls, pre-pour | Base and vapor barrier, when used–driveways | 3,000 sq. ft. area or less | $55 each structure |
Concrete floors or walls, pre-pour | Base and vapor barrier, when used | Each additional 1,000 sq. ft. or fraction thereof | $25 each additional |
Concrete floors or walls, pre-pour | Concealed utilities | 3,000 sq. ft. area or less | $55 each structure |
Crawl | 2,500 sq. ft. or less | $10 each additional 1,000 sq. ft. area or fraction thereof | $55 |
Deck, pre-pour | $55 | ||
Drywall hanging | $55 | ||
Electrical service, new or change | 100 amp or less | $160 each service | |
Electrical service, reconnect | 100 amp or less | $75 plus inspection fee of $55 | |
Electrical service, new or change | Each additional 100 amp or fraction thereof | $60 | |
Electrical service, reconnect | Each additional 100 amp or fraction thereof | $60 | |
Electrical service, new or change–subpanel | Addition of new branch circuits with service change or remodeling only | Per panel | $60 |
Erosion control | Property check | $55 | |
Final | Use categories as for rough-in below | See rough-in fees below | |
Fireplace–mechanical | $55 | ||
Fireplace–masonry | $100 | ||
Footings | 2,500 sq. ft. in area or less | $55 each structure | |
Footings–pre-pour | 2,500 sq. ft in area or less | $55 each structure | |
Footings | Each additional 1,000 sq. ft. or fraction thereof | $25 | |
Footings–pre-pour | Each additional 1,000 sq. ft. or fraction thereof | $25 | |
Footings–pre-pour (Single Family) | 2,500 sq. ft. in area or less | $165 | |
Footings–pre-pour (Duplex) | 2,500 sq. ft. in area or less | $110 | |
Footings–pre-pour (Town Home) | 2,500 sq. ft. in area or less | $80 | |
Foundation | 2,500 sq. ft. in area or less | $55 each structure | |
Footings–pre-pour | 2,500 sq. ft in area or less | $55 each structure | |
Foundation | Each additional 1,000 sq. ft. or fraction thereof | $25 | |
Footings–pre-pour | Each additional 1,000 sq. ft. or fraction thereof | $25 | |
Ice/shield roof | $55 each | ||
Insulation | 5,000 sq. ft in area or less | $55 | |
Insulation | Each additional 1,000 sq. ft. or fraction thereof | $25 | |
Maintenance/repair, deck | Plus inspection(s), as needed | $50 base fee | |
Maintenance/repair, re- roofing, downspouts, fascia/gutter | Plus inspection(s), as needed | $50 base fee | |
Maintenance/repair, siding/exterior change | Plus inspection(s), as needed | $50 base fee | |
Maintenance/repair, HVAC, plumbing, hot water tank | Plus inspection(s), as needed | $50 base fee | |
Masonry | $55 | ||
Parking lots, multi-family and condominiums only | Subgrade–engineering | One hour minimum | Per engineering fee |
Parking lots, multi-family and condominiums only | Pre-pavement–engineering | One hour minimum | Per engineering fee |
Re-inspections | Any of: footings, foundation, concrete floors or walls (pre-pour), electrical service (new or change), rough-in, or final | $50 flat fee | |
Rough-in | Total fee | Total of plumbing, HVAC, electric, and framing fees below | $220 minimum |
Rough-in | Plumbing | 3 bathrooms or less | $55 each structure |
Rough-in | Plumbing | Each additional bathroom | $25 per bathroom |
Rough-in | HVAC | 3,000 sq. ft. of conditioned space or less | $55 each structure |
Rough-in | HVAC | Each additional 1,000 sq. ft. or fraction thereof | $25 |
Rough-in | Electric | 3,000 sq. ft. floor space or less | $55 each structure |
Rough-in | Electric | Each additional 1,000 sq. ft. or fraction thereof | $25 |
Rough-in | Framing | 3,000 sq. ft. of floor space or less | $55 |
Rough-in | Framing | Each additional 1,000 sq. ft. or fraction thereof | $25 |
Temporary occupancy fee | To convert temporary occupancy to final | $110 | |
Window replacement | Plus inspection(s), as needed | $50 base fee | |
Driveways, replacement | Plus inspection(s), as needed | $50 base fee | |
Irrigation systems | Requires testing agent | $75 | |
Others as required–3 units or more | Fire Code, when required | As set by Fire Prevention Bureau | As given in § 150.25 |
Others as required | Miscellaneous (not listed above), when required | As determined by Building Administrator | |
Sanitary sewer line connection | $55 | ||
Violations inspection | $225 each violation | ||
(H) Relocated structure or building permit fees, residential. The same fees apply as are applied above to new construction.
(I) Demolition fees.
Demolition Fees, Residential | |
Type of Structure | Fees |
All accessory buildings | $40 each structure |
Multi-family and condominiums | $100 for first 5,000 sq. ft. and $25 for each 600 sq. ft. thereafter |
One- and two-family residence | $75 each structure |
Required inspections | Use schedule above |
Engineering fees if required | Paid by permit holder |
(J) Minimum fees, residential. No permit fee for a construction or remodeling project shall be less than $50. The zoning fee if required, the cost of any required inspection fees as listed above, and the cost of a certificate of occupancy if required, are additional costs. The minimum permit fee does not apply to a fence-only permit or demolition permits.
(K) Basement conversions to living space. Reduced fee basements for which permit fees were paid under division (B) of this section are given a special rate for remodeling that converts any existing area of the basement to living space. The special rate is calculated by subtracting the basement rate from the living space rate. Rates used in the calculation are as of the day the remodeling permit is approved. Other applicable fees are at rates stated in the above divisions. The reduced fee is not available for basement additions.
(L) Foundation-only permits, residential; optional.
(1) A permit for a structure foundation may be issued prior to the application for and approval of permits required under divisions (B) and (C) above. The Town Building Administrator and the Town Engineer shall set guidelines for information required to be submitted. Consideration of this type of permit is restricted as described in § 150.28(D) of this code.
(2) The applicant will complete a waiver approved by the Plan Commission Attorney as part of the requirements for the permit.
(3) The scope of this permit is limited to footings, foundation walls of which at least 51% will be below grade, and concrete floors at or below grade. Plumbing, electrical, and HVAC work is limited to those specific items needed prior to backfilling and/or pouring concrete floors.
(4) This permit expires in 30 days from issuance unless a complete application for a building permit as required in divisions (B) or (C) of this section is filed with the Building Administrator prior to expiration unless the Building Administrator approves for extension prior to expiration. Once the building permit required in this section is approved and released by the Building Department, the applicant shall pick up and pay for the building permit within 30 days of the date of notification by the Building Department.
(5) (a) The fees shall be as given in division (F) above. All necessary inspection fees will be charged per division (G) above.
(b) A credit will be issued for the portion of the valid foundation-only permit fee based on square footage to be used only for the subsequent building permit. The credit is limited to the amount of the building permit fee based on square footage under division (B) or (C) above, whichever is applicable, for the same structure as the foundation-only permit. No credit will be given for expired foundation-only permits.
(6) If this permit expires, no fees will be credited or refunded, and the applicant must re-apply for a foundation-only permit or make application for a full permit under division (B) or (C) above.
(M) Street, alley, sidewalk, public way opening permit fees.
Type of Permit | Comments | Fees |
Street opening | Any cut or opening made. | $250 |
Alley opening | Any cut or opening made. | $250 |
Sidewalk opening | Any cut or opening made. | $250 |
Rights-of-way turf opening | Any cut or opening made. | $125 |
Type of Inspection | Comments | Fees |
Street and alley | Any cut or opening made. | Direct cost reimbursement |
Sidewalk | Any cut or opening made. | Direct cost reimbursement |
Public way | Any cut or opening made, including turfed areas. | Direct cost reimbursement |
(1) Each permit for making an opening shall be confined to a single project, and shall be issued by the executive or other duly designated town representative. Application shall be made on a form proscribed by the Town Council providing the exact location of the proposed opening, the kind or type of paving, turf or fill, the area and depth to be excavated, and such other facts and information as may be required. The town and/or the Town Engineer reserves the right to impose reasonable conditions upon the applicant, as well as the right to deny the application in order to protect town improvements or upon a finding that a less intrusive method exists.
(2) No permit shall be issued until or unless the applicant tenders and pays the fee required in conformance with the schedule contained hereinafter. The permit fee is in an amount reasonably calculated to cover at least a portion of the cost of restoration and maintenance of the opening, as well as all other related administrative expenses thereto.
(3) All such fees collected for the purposes stated herein shall be deposited in the town’s General Fund for use consistent with the requirements of this chapter, as amended hereafter from time to time.
(4) The opening, restoration and maintenance of a pavement or other surface shall be performed under the direction and to the satisfaction of the Town Engineer, or other duly designated town representative, and in accordance with rules, regulations, and specifications approved by the Town Council.
(5) In the event of the failure and/or refusal of the permittee to satisfactorily fill the excavation, restore the surface and remove all excess materials in accordance with the terms of the permit, and within the time specified in the permit, or where such time period is not specified in the permit within a reasonable time, the town may proceed to make such fill and restoration. In the event the amount of the costs incurred by the town exceed the amount of the restoration services performed by it, the town shall be entitled and permitted to collect any excess amount due and owing from the permittee, including attorney’s fees, court costs, and similar related expenses of collection.
(Ord. 41, passed 2-18-1998; Am. Ord. 41A, passed 3-17-1999; Am. Ord. 41B, passed 3-18-2004; Am. Ord. 120, passed 11-16-2004; Am. Ord. 41D, passed 2-12-2006; Am. Ord. 41E, passed 3-21-2006; Am. Ord. 41F, passed 12-16-2008; Am. Ord. 41H, passed 10-20-2009; Am. Ord. 41I, passe 2-15-2010; Am. Ord. 210, passed 9-11-2012; Am. Ord. 41-J, passed 9-24-2013; Am. Ord. 41-K, passed 10-8-2019; Am. Ord. 41-L, passed 3-8-2022)