To the maximum degree possible, the following objectives shall be met for new construction, building expansion or site modification:
(a) Storm water draining from the site shall not exceed that occurring under natural land cover conditions unless the system is designed to accommodate the flow.
(b) Existing natural drainage courses, wetlands, and water bodies should be preserved whenever feasible.
(c) Storm water detention basins and other open space and natural vegetative areas may be required as part of the water management system.
(d) Water absorptive paving and water detention design may be required in areas where practical.
(e) The overall storm water management system should be designed to accommodate the "100 year frequency storm".
(Ord. 1997-117. Passed 9-16-97.)