§ 154.018 PLOT PLAN AND BUILDING PERMIT.
   (A)   A plot plan (§ 154.044 of this chapter) along with required fees (§§ 154.055 through 154.057 of this chapter) shall be submitted to the City Planner.
   (B)   For work within the Main Street District, including the Historic Preservation District, copies of the plot plan and supporting documents shall be forwarded to the Main Street Design Committee for review.
   (C)   The applicant shall consult with the Chief Building Official for general information regarding requirements for plot plan and building permit applications and special considerations pertaining to the site. A sketch plan should be brought in for more complex projects to show the concept of the site development.
   (D)   Each reviewing city department shall review all plot plan applications on Monday and/or Tuesday of each week and upon review shall approve or shall approve subject to specific conditions being met. This ensures that all applications shall be reviewed by staff within six working days.
   (E)   Applicant meets with the Chief Building Official to review recommendations of the various departments. Further consultation with the various reviewing departments may be necessary to reach agreement on changes in the plot plan. Design and service oriented issues (not code or ordinance requirements) may be appealed to the Planning and Zoning Commission for final determination.
   (F)   The applicant shall make final changes as agreed and submit four copies of the approved plot plan to the Chief Building Official.
   (G)   The City Engineer will then prepare a memorandum of agreement for public improvements setting forth the applicant’s financial assurance that all required public improvements will be completed to city standards, requirements and specifications (§ 154.073 of this chapter). The memorandum of agreement for public improvements must be signed by the applicant prior to issuance of the building permit.
   (H)   The applicant is then eligible for a building permit and submits the following to the Chief Building Official:
      (1)   Building permit application form; and
      (2)   Two sets of building plans.
   (I)   The building plans will then be reviewed by the city staff or referred to the city’s architecture or engineering consultant.
   (J)   The building permit is issued by the Chief Building Official upon approval of the application and building plans and payment of the required fees.
(Prior Code, § 10-2.04) (Ord. 747, passed - -1995; Ord. 895, passed - -2008)