§ 154.062 COMPLETION OF IMPROVEMENTS.
   (A)   A final plat may not be approved until:
      (1)   All required improvements have been completed; or
      (2)   A subdivision guarantee has been provided in accordance with § 154.063.
   (B)   An improvement will be deemed completed only after the appropriate public agency certifies that the improvement has been installed in accordance with the approved final plat and improvement plan. In lieu of certification from a public agency, the Chief Subdivision Engineer is authorized to accept certification from the applicant’s registered professional engineer that the improvements have been installed in accordance with all applicable standards.
(Ord. passed 7-8-1970; Res. 09-167, passed 6-18-2009)