1305.60 ARCHITECTURAL REVIEW BOARD.
   There is established an Architectural Review Board that will meet on an as-needed basis to consider applications for buildings, additions, and alterations to existing buildings along Euclid Avenue within the City of Wickliffe. No permit for new building, additions, or alterations to existing structures will be issued until compliance with the following requirements has been met:
   (a)   Four sets of drawings are required for all of the following submittals except as noted. All drawings shall be drawn to the scale indicated and shall be stamped by an architect or engineer registered in the State of Ohio. An index of all drawings shall be indicated on the first sheets.
      (1)   Site Plan  (1” = 40’)
         The site plan must show the location of the building on the parcel.
   Outlines of buildings on adjacent parcels must also be shown. The plan must show the footprint of the building with the following items dimensioned:
         A.   Front, side, and rear yard setbacks. Review zoning and any deed restrictions with the Building Department.
         B.   Location of proposed building in relation to the street, any drives, parking areas, tree lawn, parking lots, parking islands, and any other adjacent structures exposed on Euclid Avenue.
         C.   The site plan shall also show the following items:
            1.   Permanent parcel number, sublot number, address
            2.   All dimensions
            3.   Location of all chimneys, overhangs and stairways as they relate to the setback requirements
            4.   Location of any easements
            5.   Grading and drainage plan, including all necessary existing and proposed catch basins and drainage piping, including downspouts
            6.   All finished floor elevations
            7.   Finished grades and location of existing structures on adjacent properties. First-floor elevations for existing structures on adjacent properties.
            8.   Height relationship information for structures on adjacent properties.
      (2)   Floor, Foundation, and Roof Plans (minimum scale 1/8” = 1’)
         A.   Foundation plans must include a complete footer and foundation plan and must indicate, at a minimum, the following:
            1.   Footings dotted
            2.   Complete structural framing information
            3.   Complete drainage information including footer drains and downspouts
   (b)   Floor plans shall be complete and show all new construction. If the project is an alteration or an addition, the plans shall show the entire existing structure. Plans must, at a minimum, indicate the following:
      (1)   Locations of all major elements of the plan, walls, windows, doorsteps, appliances, chimneys, fireplaces, etc.
      (2)   Electrical plans and HVAC plans may be shown on the plans or on separate electrical and mechanical plans.
      (3)   Floor plans shall indicate the structural framing information.
   (c)   Roof Plan shall indicate all elements, parapets, elevator penthouses, etc. If an addition, the plans must show the existing structure.
      (1)   Wall Sections    (minimum scale ½” = 1’)
   Wall sections from below the footer to above the highest element on the roof shall be submitted. A typical wall section may be permitted if the structure is the same on all sides. Sections through overhangs or special and significant architecturalelements shall also be provided. Notations shall indicate the type of materialsbeings used, dimensions, and insulation values.
       (2)   Exterior Elevations (minimum scale 1/8” – 1”)
   Exterior elevations shall be provided for all sides of a new structure and any side modified by an alteration or addition. Any submission which does not provide all the necessary elevations will be deemed not complete.Exterior elevations shall include the following information. The information shall be shown in a graphic format with annotations.
         A.   Exterior materials proposed. Additions or alterations shall match existing materials, including existing colors.
         B.   Show all proposed openings, doors, windows, etc.
         C.   Provide a color schedule of all elements.
         D.   Elevations shall show relationships to existing surrounding adjacent buildings (including those to the rear) showing the height of elements and the distance from those structures.
         E.   It is suggested that a colored rendering of the exterior elevation of commercial, institutional, and multi-family buildings be presented at the time of review. The colors should be similar to the materials being proposed.
         F.   If rooftop HVAC equipment is proposed, or if there are any architectural elements on the roof, these also must be shown and it must be shown how they will be concealed from view. This may be shown in the elevations or it may be necessary to submit a building cross section.
      (3)   Photographs. One set ofcolor photographs of the exterior shall be submitted. Photographs shall be ofall sides of existing structures where possible or applicable. Photographs of commercial buildings shall show adjacentstructures. Photographs of new structures shall show vacant land and the structures on either side of the proposed construction.
      (4)   Material Samples. All exterior finished materials including roofing. One set of samples of proposed materials shall be submitted. If the proposed materials match existing materials, samples need not be submitted.
      (5)   Cash Deposit. A cash deposit of a minimum of five hundred dollars ($500.00) shall be submitted with application. Checks will be made payable to the City of Wickliffe.
      (6)   Fee. A fee of one hundred dollars ($100.00) per hour for Architectural Review will be charged to each applicant, said fee to be determined by the Building Commissioner.
         (Ord. 2005-35. Passed 3-28-05.)