§ 51.46 CAPACITY CHARGE.
   Each property owner requesting water service shall pay a capacity charge. At the time an application for a building permit is filed, the applicable water capacity charge shall be paid in accordance with the following schedule.
Meter Size (inches)
Phase I/Phase II
Capacity Charge
Meter Size (inches)
Phase I/Phase II
Capacity Charge
5/8
$1,035
3/4
1,490
1
2,650
1-1/2
5,962
2
10,598
3
23,846
4
42,394
 
(Ord. 2006-05, passed 4-10-06; Am. Ord. 8-04, passed 6-9-08; Am. Ord. 08-4A, passed 9-8-08)