The subdivider shall be required to pay for all of the construction costs for the installation of utilities which are serving the proposed subdivision as approved by the Village and the Subdivider's Estimates. The Village may elect to have the utilities over-sized to service the surrounding areas, providing the improvement is beneficial to the Village. The Village shall pay the difference between the cost of the requirements of the subdivision and required over-sizing improvements as follows:
(a) Water Mains. A subdivider shall install water mains according to the Village's specifications. The material's cost difference between the minimum required size of pipe and appurtenances, and over-sized pipe required by the Village, will be paid by the Village.
(b) Sanitary Sewers. A subdivider shall install sanitary sewers according to the Village's specifications. The material's cost difference between the minimum required size of pipe and appurtenances, and over-sized pipe required by the Village, will be paid by the Village. The construction cost difference as determined by the Village Engineer for the minimum depth needed for installation, and the greater depth of installation required by the Village, will be paid by the Village.
(c) Storm Sewers. A subdivider shall install storm sewers according to the Village's specifications. The material's cost difference between the minimum required size of pipe and appurtenances, and over-sized pipe required by the Village, will be paid by the Village. The construction cost difference as determined by the Village Engineer for the minimum depth needed for installation, and the greater depth of installation required by the Village, will be paid by the Village.
(d) Streets. The type and composition of street paving and surfacing shall be installed as per current Village specifications, or County Engineering specifications where applicable, and shall be commensurate with the volume, street classification, character, and general circulation requirements, as determined by the Village. The cost of materials for the paved surface and its sub-base of an existing street, and any over-sizing cost in excess of the owner's required responsibility needed to meet the dimensional standards for roadways, as shown on the Village Comprehensive Development Plan, shall be at the Village's expense. The costs for the minimum street width, as required by these Regulations, including curb, gutter, and sidewalks, shall be the developer's responsibility and at his or her expense.
(Ord. 2021-17. Passed 9-8-21.)