(a) Water used during construction shall be metered and billed to the applicant for water service at the water rates in effect. A water meter shall be installed after application is made for service and the corresponding tap-in fees and water service connection charges paid.
(b) Should a meter not be installed, the monthly minimum rate will be charged plus estimated usage. Any damage to the water meter during the construction period will be the responsibility of the water service applicant.
(Ord. 515. Passed 3-26-90.)