1369.03 BOND; REPAIRS AND REPLENISHMENT.
   Before a permit is issued for the construction of any building within the City, the builder shall post with the Director of Finance a cash bond in the amounts for the types of buildings hereinafter set forth:
   (a)   Residential:
 
New single family dwellings per each
$500.00
New multi-family up to 5 units
500.00
New multi-family over 5 units, per unit
100.00
 
   (b)   Commercial, Business and Industrial Uses:
 
Square Feet
 
0 - 5,000
$2,000.00
5,000 - 10,000
4,000.00
10,000 - 20,000
5,000.00
20,000 - 30,000
6,000.00
Over 30,000
8,000.00
 
   (c)   Any construction requiring a greater deposit than indicated in the above schedule shall be determined by the Mayor, the Director of Inspections and additional department directors as may be involved.
   In the event that the Director of Inspections determines, after inspection, that any public property located between the lot on which a building is being constructed and the adjacent streets or roadways has been deposited with mud or debris; has been damaged by the passage of vehicles or equipment to and from the lot; and that such damage could have been avoided by the construction and/or maintenance of an adequate temporary or permanent driveway in compliance with Section 1369.01; the Director of Inspections shall have authority to authorize the removal of mud and debris or the repair of such damage. The expense of repairs shall be paid for from the cash bond required by this section. If more than the cash bond is used for repairs, the builder shall, before proceeding with further construction and within three days after being notified by letter mailed by first class mail to the builder's address, as set forth in the building permit, replenish such bond by posting sufficient money with the Director of Finance to restore the cash bond required by this section.
(Ord. 1990-99. Passed 5-3-90.)