13-7-1: CONSTRUCTION OBSERVATION:
   A.   All infrastructure improvements required for the development shall be observed during the course of construction by the Subdivision Administrator. All reasonable fees (including reasonable attorney fees, engineering fees and/or staff costs) associated with such activity, including the reviewing of the plans and specifications for such improvements, shall be paid for by the applicant. The applicant may be required to post a deposit with the City to cover the anticipated costs of such services before they are undertaken. In the event that these fees are not paid in a timely manner, the City may, at its sole discretion, draw down on any subdivision improvement/maintenance security which may be available.
   B.   The applicant shall give at least forty eight (48) hours’ written notification to the Subdivision Administrator prior to the performance of any of the following:
      1.   The construction of any roadway or street.
      2.   The surfacing of any roadway or street.
      3.   The installation of any curbing or gutters.
      4.   The grading or backfilling of any open trench or excavation in which any utility facilities, including, but not limited to, water lines, sewer lines, and electrical cables, have been installed.
      5.   The construction of any sidewalk.
      6.   The filling, pressure testing, chlorination, or water sampling of any water main.
   C.   Within the forty eight (48) hour notice period, the Subdivision Administrator may conduct on-site observation to determine that the proposed work complies with the engineering drawings. If, in the opinion of the Subdivision Administrator, the proposed work does not comply with such final drawings, the Subdivision Administrator shall have the authority to order that all such proposed work be terminated until such time as necessary steps are taken to correct any defects or deficiencies. Upon the correction of such deficiencies, the applicant shall again notify the Subdivision Administrator.
   D.   There shall be no development work on Sundays. Development work is allowed on Saturdays, but any necessary City inspections/testing observation must be preapproved and coordinated with the Subdivision Administrator. Development work hours shall be from sunrise to sunset (see also subsection 5-8-2G and section 11-11-13 of this Code).
(Ord. 2420, 6-24-2014)