939.06  APPLICATION PROCEDURES.
   (a)   Soil disturbing activities submitting a storm water pollution prevention plan:  The applicant shall submit the SWP3 and the applicable fees to the City of Waterville or the City's authorized reviewing agent as follows:
      (1)   For subdivisions: With submittal of the improvement plans.
      (2)   For other construction projects: Before issuance of a zoning permit by the City.
      (3)   For general clearing projects: Prior to the commencement of any clearing activity at the site.
   (b)   The City of Waterville or the City's authorized reviewing agent shall review the plans submitted under 939.06 (a) for conformance with this regulation and approve, or return for revisions with comments and recommendations for revisions.
   (c)   Soil disturbing activities shall not begin and zoning permits shall not be issued without an approved SWP3.  The City's authorized reviewing agent shall be notified not less than three (3) working days before any soil disturbing activities begin.  Failure to comply with this requirement may be considered a violation of this regulation and the City of Waterville may take enforcement action as detailed in this Chapter.
   (d)   SWP3s for individual lots in a subdivision will not be approved unless the larger common plan of development or sale containing the lot is in compliance with this regulation.
   (e)   Approvals issued in accordance with this regulation shall remain valid for one (1) year from the date of approval.
(Ord. 06-16.  Passed 5-9-16.)