Before any permit is issued, the Commissioner's Office shall collect the following fees as the case may be:
(A) A fee of $500 which will be reimbursed within 90 days of proper completion of a cut repair. The approval committee mentioned in § 97.045 will have the discretion to waive the $500 fee if a contractor has done work for or in the city for a minimum of two years and is in good standing with the city.
(B) A fee $.20 per square foot for cutting any gravel, rock or unpaved street, or for cutting any concrete curb or gutter or sidewalk. The minimum fee shall be $2.
(C) A fee of $.20 per square foot for excavation in unpaved alleys.
(Prior Code, § 97.57) (Am. Ord. 12-2013, passed 7-8-2013)