The SWP3 and Abbreviated SWP3 review, filing, and inspection fee is part of a complete submittal and is required to be submitted to the City of Warren WPC before the review process begins. The current fee schedule is available on the City of Warren WPC website: https://www.warren.org/index.php/water-pollution-con/wpc-program-information. Applicants may be charged two hundred fifty dollars ($250.00) for each additional inspection that the City of Warren WPC must conduct if a site has one of the following compliance issues:
(a) Construction activities have started at the site with no SWP3 completed;
(b) Failure to install sediment basin(s) when the SWP3 and/or site drainage clearly indicate as a first step (within seven (7) days prior to grading and within seven (7) days of grubbing);
(c) Failure to implement any sediment/erosion controls; or
(d) Dewatering activities resulting in turbid discharges.
(Ord. 13158/2022. Passed 9-28-22.)