Notwithstanding this chapter, jurisdiction of the Commission over interior spaces shall be limited to specific interior features of architectural, artistic, or historical significance in publicly-owned landmarks, and of privately-owned historic landmarks for which consent for interior review has been given by the owner. If an owner's consent for interior review has been filed in the office of the Wake County Register of Deeds and indexed according to the name of the owner of the property in the grantee and grantor indexes, such consent shall bind future owners and/or successors in title. The ordinance establishing the historic designation shall specify the interior features to be reviewed and the specific nature of the Commission's jurisdiction over those features.
(Ord. passed 5-4-1992)
Nothing in this chapter shall be construed to prevent the ordinary maintenance or repair of any exterior architectural feature of a historic landmark or property located within a district that does not involve a change in design, material, or outer appearance thereof. Nor shall this chapter be construed to prevent the construction, reconstruction, alteration, restoration, moving, or demolition of any such feature when a building inspector or similar official certifies to the Commission that such action is required for the public safety because of an unsafe or dangerous condition. Nothing herein shall be construed to prevent a property owner from making any use of his property not prohibited by other statutes, ordinances, or regulations. Nothing in this chapter shall be construed to prevent the maintenance of or, in the event of an emergency, immediate restoration of any existing above-ground utility structure without approval by the Commission.
(Ord. passed 5-4-1992)
(A) The Commission staff may issue a Certificate of Appropriateness for minor works, as listed in the Commission's Rules of Procedure. Minor works shall include and are defined as those exterior changes that do not involve substantial alterations, additions, or removals that could impair the integrity of the property and/or district as a whole.
(B) No application for a minor works Certificate of Appropriateness may be denied without formal action by the Commission.
(Ord. passed 5-4-1992)
(A) Except as provided below, the Commission may not deny an application for a Certificate of Appropriateness authorizing the demolition of a designated historic landmark or property located within a district. However, the Commission may delay the effective date of such a certificate for a period of up to 365 days from the date of approval. The Commission may reduce the period of delay where it finds that the owner would suffer extreme hardship or be permanently deprived of all beneficial use of or return from such property by virtue of the delay. During such period, the Commission may negotiate with the owner and with any other parties in an effort to find a means of preserving the property, as provided in section § 151.019 (Q).
(B) The Commission may deny an application for a Certificate of Appropriateness authorizing the demolition or destruction of a building, site, or structure determined by the State Historic Preservation Office to have statewide significance, as defined in the criteria of the National Register of Historic Places, unless the Commission finds that the owner would suffer extreme hardship or be permanently deprived of all beneficial use or return by virtue of the denial.
(C) If the Commission has voted to recommend designation of a property as a landmark or designation of an area as a district, and final designation has not been made by the local governing body, the demolition or destruction of any building, site, or structure located on the property of the proposed landmark or in the proposed district may be delayed by the Commission for a period of up to 180 days or until the local governing body takes action on the designation, whichever occurs first. Should the governing body approve the designation prior to the expiration of the 180 day delay period, an application for a Certificate of Appropriateness for demolition must then be filed; however, the maximum delay period of 365 days shall be reduced by the period of delay while the designation was pending.
(Ord. passed 5-4-1992; Ord. O-93-19, passed 9-20-1993)
Demolition by neglect of any designated historic landmark or property located within a district shall constitute a violation of this chapter. The local governing body may take appropriate actions to prevent demolition by neglect, provided such actions include appropriate safeguards to protect the property owner from undue economic hardship.
(Ord. passed 5-4-1992)
(A) Submittal of application. An application for a Certificate of Appropriateness shall be obtained from and, when completed, filed with the Commission staff. Applications for Certificates of Appropriateness shall be considered by the Commission at its next regularly scheduled meeting, provided they have been filed, complete in form and content, at least ten working days before the meeting; otherwise consideration shall be deferred until the following meeting.
(B) Contents of application.
(1) The Commission shall, by uniform rule in its Rules of Procedure, require information as is reasonably necessary to determine the nature of the application. An application for a Certificate of Appropriateness shall not be considered complete until the required information is included. An incomplete application shall not be accepted.
(2) Nothing shall prevent the applicant from filing with the application additional relevant information bearing on the application.
(C) Notification of affected property owners. Before considering an application for a Certificate of Appropriateness, the Commission shall notify by mail the owners of any adjacent property. The mailed notices are for the convenience of the property owners and occupants and any defect or their omission therein shall not impair the validity of issuing a Certificate of Appropriateness, or any following action.
(D) Hearing. When considering an application, the Commission shall give the applicant and owners of any property likely to be materially affected by the application, an opportunity to be heard.
(E) Commission action on application.
(1) When considering the application, the Commission shall apply the review guidelines required by § 151.002, and shall, before final action of the application, make findings of fact indicating the extent to which the application is or is not in compliance with the review criteria.
(2) The Commission's action on the application shall be approval, approval with modifications, deferral, or disapproval.
(F) Reasons for Commission's actions to appear in minutes. The Commission shall cause to be entered into the minutes of its meeting the reasons for its actions, whether it be approval, approval with modifications, deferral or denial. The minutes shall also contain a summary of any citation to the evidence, testimony, studies, or other authority upon which it based its decision.
(G) Time limits.
(1) If the Commission fails to take final action upon any application within 90 days after the complete application is submitted to the Commission staff, the application shall be deemed to be approved as submitted. This time period may be extended upon mutual agreement between the Commission and the applicant.
(2) A Certificate of Appropriateness shall expire six months after the date of issuance, or in the case of a demolition Certificate of Appropriateness, the effective date, if the work authorized by the certificate has not been commenced. If the work has been discontinued for a period of 12 months after commencement, the permit shall immediately expire.
(H) Submission of new application. If the Commission denies a Certificate of Appropriateness, a new application affecting the same property may be submitted only if substantial change is made in plans for the proposed construction, reconstruction, alteration, restoration, or moving.
(I) Appeals of the Commission's decision. An appeal may be made to the Board of Adjustment of the corresponding jurisdiction regarding the Commission's action in approving or denying any application for a Certificate of Appropriateness. Written notice of intent to appeal must be sent to the Commission, postmarked within 20 days following the Commission's decision, unless oral notice of appeal is made to the Commission during the meeting at which the decision is rendered. Appeals must be filed with the Board of Adjustment of the corresponding jurisdiction within 60 days following the Commission's decision. Appeals shall be in the nature of certiorari. The Board of Adjustment's decision in any such case may be appealed to the superior court of Wake County.
(Ord. passed 5-4-1992)
Designated historic buildings, structures, sites, areas, or objects owned by the state or any of its political subdivisions, agencies, or instrumentalities shall be subject to the regulations imposed by this chapter, in accordance with G.S. § 160D-947.