At least three days prior to the date of the actual move a completed application form shall be submitted to the city engineer on an approved application form. The following information shall be included on the application:
A. The kind of structure to be moved;
B. The street location or other identifying description of the site to which the structure is to be moved;
C. The route over, along, across, and upon which such structure is to be moved;
D. The time it is proposed to move the structure and within which removal will be completed;
E. Signatures from the following utility companies acknowledging that they have seen and approved the proposed route over which the structure is to be moved;
1. Southern California Edison,
2. Pacific Bell,
3. Continental Cablevision;
F. The loaded height;
G. The loaded length;
H. The loaded weight;
I. The type and number of wheels of the truck or dolly;
J. Other information as required by the city engineer to review the application. (Prior code § 7841(c))