A. Pavement and base shall be replaced in accordance with the requirements of the City of Visalia Engineering Standard Specifications and Engineering Standard Details, current edition.
B. All surfacing material removed for the work proposed is to be disposed of off the public right-of-way. The backfill is to be compacted in accordance with the requirements of the City of Visalia Engineering Standard Specifications and Engineering Standard Details, current edition All necessary compaction and materials tests are to be paid for by the permittee unless it is called out as the responsibility of a contractor working on behalf of the city.
C. No pavement shall be replaced until the backfill and base have been inspected and approved by the city engineer or designee. (Ord. 2013-07, 2013)