A. A C&D Debris Recycling and Reuse Plan shall be approved or denied no later than thirty (30) days after a complete application is made.
B. Notwithstanding any other provision of this chapter, no permit shall be issued for any covered project unless and until the C&D Debris Recycling and Reuse Plan has been approved.
1. All of the information has been remitted on the C&D Debris Recycling and Reuse Plan.
2. The C&D Debris Recycling and Reuse Plan establishes a mechanism such that the diversion requirement shall be met.
C. If the Director determines that the C&D Debris Recycling and Reuse Plan application is incomplete or fails to indicate that one hundred percent (100%) of inert solids and at least fifty percent (50%) by weight of all construction and demolition debris generated by the project will be reused or recycled, he or she shall either:
1. Return the C&D Debris Recycling and Reuse Plan application to the Building Official marked "Denied", including a statement of reasons, which shall then immediately stop processing the building or demolition permit application; or
2. Return the C&D Debris Recycling and Reuse Plan to the Building Official marked "Further Explanation Required".
D. Within 30 days following project completion, a final compliance report containing the following information and documentation must be submitted to the Building Official, listing every vendor or facility that collected, transported or received any C&D debris.
1. Copies of receipts from every vendor or facility that collected, transported or received any project C&D debris. Each receipt must specify the weight of any project C&D debris handled by the vendor or facility and must clearly demonstrate that all such C&D debris originated from the project site.
2. A calculation of the actual percentage, determined by weight, of project C&D debris that was recycled or reused for each vendor or facility that collected, transported or received material.
3. A description of the manner in which the project C&D debris was recycled or reused and the name and address of all vendors and facilities employed in the recycling or reuse of project C&D debris, including the recycling or reuse rate of each vendor or facility, as applicable.
E. Failure to accurately account for and submit the required documentation for all project C&D debris in the final compliance report constitutes a violation of this chapter. (Ord. 2005-24, 2005)