Section 9-2035.01   Plat submitted.
   (a)   The subdivider shall submit five (5) copies of the final plat, so marked, to the Subdivision Administrator not less than twenty (20) days before the Planning Board meeting at which the approval of the plat is to be considered. One additional copy shall be prepared under G.S. 47-30 and shall bear all the required certifications outlined in Section 9-2035.04 of this chapter, at which time it will be considered for approval.
   (b)   The reproducible drawing shall be given to the Subdivision Administrator not later than the date of the Planning Board meeting at which approval is requested. The plat shall be submitted not more than twelve (12) months after the date on which the preliminary plat was approved; provided, however, a written extension of this time limit may be granted by the Planning Board on or before the first anniversary of the approval. (Ord. of 11/3/08; Ord. of 6/28/21)