§ 12-8E-19 TIME REQUIREMENTS.
   (A)   Start of construction; completion. The developer must begin initial construction of the development plan within three years from the time of its final approval, and continue diligently toward the completion of the project. If the development plan is to be developed in phases, the developer must begin construction of subsequent phases within one year of the completion of the previous phase.
   (B)   Approval voided. If the developer does not begin and diligently work toward the completion of the development plan or any stage of the development plan within the time limits imposed by the preceding subsection (A), the approval of said development plan shall be void. The Planning and Environmental Commission shall review the development plan upon submittal of an application to reestablish the development plan following the procedures outlined in § 12-8E-7 of this article.
(Ord. 4(2003) § 1; Ord. 29(2005) § 25)