§ 154.077 PRELIMINARY PLAN REQUIREMENTS.
   See § 154.076(A) regarding when a preliminary plan is required.
   (A)   (1)   All of the following information and materials listed in this section are required as part of all preliminary plan submissions for any land development and any major subdivision. This list of requirements shall serve both:
         (a)   To establish the requirements; and
         (b)   As a checklist for the applicant and the township to use to ensure completeness of submissions.
      (2)   The applicant shall submit completed photocopies of division (C) below as part of the application.
   (B)   The required information listed in this section may be combined or separated onto different sheets, provided that all information is clearly readable.
   (C)   Preliminary plan for major subdivision or land development.
Upper Milford Township Preliminary Plan for Major Subdivision or Land Development**
Checklist and List of Submittal Requirements
Applicant’s Name: _________________________________________________________________
Applicant’s Address: ________________________________________________________________
Applicant’s Daytime Phone No(s).: _____________________________________________________
Applicant’s Signature: ______________________________ Date of Submittal: __________________
* Place checkmarks in the appropriate columns below, except: 1) insert “NA” in the “Not Submitted” column if not applicable and 2) insert “W” in the “Not Submitted” column if a waiver is requested from the requirement. A written request for any waiver or modification is also required under § 154.007
** See § 154.076(A) concerning which types of “land developments” are required to submit a preliminary plan
Submitted   Not
           Submitted*
         A. GENERAL SUBMISSION ITEMS: (Note - the township may require the submission of additional numbers of copies)
________   __________   1. 3 copies of completed township application (see Appendix A)
________   __________    2. Required township review fee(s)
________   __________    3. Required township escrow funds (to fund reviews)
________   __________    4. 2 copies of the preliminary plan checklist (using the photocopies of the pages in this section)
________   __________    5. 11 print copies of the complete preliminary plans, with original signatures and seals of plan preparers on one “File Copy”
________   __________    6. 2 additional print copies of only the layout plans, black and white, at a maximum size of 11 in. x 17 in.
________   __________    7. 2 sets of supportive documents
________   __________    8. Notification that applicant provided a copy of the plan to the Lehigh Valley Planning Commission for review
________   __________    9. Aerial photo. An applicant for a major subdivision is requested but not required to submit an aerial photo (current if available) of the site, with the boundaries of the site highlighted
________   __________    10. A digital copy of the plans in PDF format, or other format acceptable to the township
         B. DRAFTING REQUIREMENTS: All information shall be legibly and accurately presented
________   __________    1. Plans prepared on a standard sized sheet (such as 18 in. x 24 in., 24 in. x 36 in., 30 in. x 42 in. or 36 in. x 48 in.). A plan shall not be smaller than 18 in. by 24 in. in size. All copies of plans should be folded to approximately 9 in. x 12 in. size in such a manner that the title of the sheet faces out, except exceptionally large and thick sets of plans may be rolled
________   __________    2. Plans drawn to scale of 1 inch = 50 feet or other scale pre-approved by the Township Engineer
________   __________    3. All dimensions set in feet and decimal parts thereof, and bearings in degrees, minutes and seconds
________   __________    4. Differentiation between existing and proposed features
________   __________    5. Boundary line of the parcel, shown as a heavy boundary line
________   __________    6. If layout plans involve 2 or more sheets, a map of the layout of the entire project at an appropriate scale on one sheet, and a key map showing how the sheets connect
________   __________    7. If the parcel(s) crosses a municipal boundary, a map showing both the portions in the township and the other municipality(ies), in sufficient detail for the township to determine how the parts will interrelate
________   __________    8. Required profiles shown at a scale of 1 in. = 50 ft. horizontal and 1 in. = 5 ft. vertical, or other scale pre-approved by the Township Engineer
________   __________    9. All sheets numbered and listed on one page
________   __________    10. Words “Preliminary Plan” and sheet title (such as “Layout Plan”) on each sheet
         C. GENERAL INFORMATION:
________   __________    1. Name of project on each sheet
________   __________    2. Name of landowner and developer (with addresses)
________   __________    3. Names and addresses of abutting property owners
________   __________    4. Lot lines of adjacent lots, and approximate locations of any buildings, common open spaces, detention basins or drainage channels existing or approved within 150 feet of the boundaries of the proposed project
________   __________    5. Notarized owners statement - see Appendix B
________   __________    6. Surveyor and plan preparer’s statement - see Appendix B
________   __________    7. Approval/review signature blocks for: Board of Supervisors, Township and Lehigh Valley Planning Commissions - see Appendix B
________   __________    8. Location map at a standard scale (such as 1 in. = 2,000 ft.) showing the boundaries of the project in relation to the approximate location of the following features within 500 feet from the boundaries of the parcel: existing and proposed streets; waterways; trails; preserved open spaces; parks; and municipal borders
________   __________    9. North arrow, graphic scale, written scale
________   __________    10. Date of plan and all subsequent revision dates (especially noting if this is a revision of a previously approved plan) with space for noting future revision dates and general type of revisions
________   __________    11. Deed Book volume and page number from Lehigh County records
________   __________    12. Tax map number and block and lot and property identification number for the parcel being subdivided
________   __________    13. A statement on the plan of proposed principal uses that are intended for each lot
         D. EXISTING RESOURCES AND SITE ANALYSIS MAP:
________   __________    1. Existing contour lines shown at the same scale as the layout plan, as follows:
               a. Shall be based on a field survey or photogrammetric procedure, with an established bench mark
               b. The contour interval shall be sufficient to determine compliance with township ordinances. An interval of 2 feet for slopes of less than 15% and 5 feet for slopes of 15% or greater is generally recommended
               c. Note: contours are not required to be shown within areas of lots of 10 acres or more that are clearly not intended to be altered as a result of this proposed subdivision or land development, unless needed to determine adequacy of stormwater management
________   __________    2. Identification of any slopes of 15 to 25% and greater than 25%
________   __________    3. The locations and names (if any) of watercourses, natural springs, ponds, lakes and wetlands
               a. Detailed delineations by a qualified professional of wetlands are required with the preliminary plan submission, with the locations accurately shown on the plan.
________   __________    4. Rock outcrops, stone fields, sinkholes and topical depressions
________   __________    5. Location of any areas within the 100-year floodplain (with differentiation between floodway and floodfringe if available from official federal floodplain maps)
________   __________    6. Approximate locations and abbreviated names of soil types, according to the U.S. Natural Resources Conservation Service or more accurate study, with identification of those that are alluvial, hydric, have a depth to bedrock of less than 3 feet, or a seasonally high water table of less than 3 feet. If such soils do not exist, that shall be stated on the plan
________   __________    7. Ridgelines and watershed boundaries
________   __________    8. Area and location of any proposed common open space
________   __________    9. If any common open space is proposed: method of ownership and entity proposed to be responsible for maintenance
________   __________    10. If any common open space is proposed: description of intended purposes, proposed improvements (such as rough grading) and any proposed recreation facilities
________   __________    11. Any proposed recreation trails, existing trails and trail easements
________   __________    12. Principal buildings estimated to be 80 years or older that could be impacted by the project, with name and description
________   __________    13. Existing and proposed utility easements and restrictive covenants and easements for purposes which affect development (stating which easements and rights-of-way are proposed for dedication to the township)
________   __________    14. Locations of treelines and existing forested areas, with a description of the approximate average trunk diameter of the older trees on the parcel (such as “less than 12 inches”)
________   __________    15. Locations of individual mature trees of greater than 18 inches trunk diameter measured at a height of 4.5 feet above the surrounding average ground level, other than trees within forested areas and treelines (not required for areas that will not be affected by the proposed plan, if so noted on the plan)
________   __________    16. Any proposed screening, buffer yards or earth berming (see zoning chapter)
________   __________    17. Areas of existing mature woods that are proposed to be protected and preserved or removed.
________   __________    18. General types, sizes and locations of any required street trees (see § 154.178), paved area landscaping (see township zoning ordinance) and any other major proposed landscaping
________   __________    19. Any proposed fencing (including height and type) and/or landscaping around stormwater basins (see § 154.167)
         E. HUMAN-MADE FEATURES: (with existing features graphically differentiated from proposed features)
________   __________    1. Existing and proposed lot lines
               a. The boundaries of lots (other than a residual lot of at least 10 acres) shall be determined by accurate field survey, closed with an error not to exceed 1 in 10,000 and balanced
               b. The boundaries of any residual parcel which is 10 acres or more may be determined by deed (Any residual lot of less than 10 acres shall fully comply with this chapter)
________   __________    2. Location of existing monuments and markers
________   __________    3. Sufficient measurements of all lots, streets, rights-of-way, easements and community or public areas to accurately and completely reproduce each and every course on the ground
________   __________    4. Existing and proposed (if known) building locations
________   __________    5. Overhead electric high-voltage lines and rights-of-way/easements
         F. ZONING REQUIREMENTS:
________   __________    1. Applicable zoning district name, district boundaries and required minimum lot area
________   __________    2. Minimum setback requirements shown for each lot
________   __________    3. Statement of type of water and sewer service proposed (such as “public water and public sewer”)
________   __________    4. Required and proposed building coverage and impervious coverage (may be stated as “typical proposed” for single-family detached homes)
         G. PROPOSED LAYOUT:
________   __________    1. Total acreage of site and total proposed number of lots and dwelling units
________   __________    2. Identification number for each lot (and for each building if more than 1 building per lot)
________   __________    3. Lot width (at minimum building setback line) and lot area for each lot
________   __________    4. Dimensions of each lot in feet
________   __________    5. Existing rights-of-way and cartway widths and locations of existing streets, including existing streets within 200 feet of boundaries of parcel
________   __________    6. Proposed rights-of-way and cartway widths and locations of existing and proposed streets, including streets within other developments within 200 feet of the boundaries of parcel
________   __________    7. Street centerline information including bearings and distances
________   __________    8. Horizontal curve data including radius, tangent, or arc length and delta, cord bearing and distance. Such information may be listed in a table, using reference numbers on a plan, provided that sufficient information is provided along each course (such as radius and arc length) such that each course can be reproduced in the field
________   __________    9. Right-of-way and curb lines with horizontal curve radii at intersections
________   __________    10. Beginning and end of proposed street construction
________   __________    11. Street improvements proposed by the applicant, including any acceleration/ deceleration lanes, traffic signal, street realignment or widening of abutting streets
________   __________    12. Any proposed curbing (place No in Not Submitted column if not proposed by applicant)
________   __________    13. Any proposed sidewalks and/or walkways (place No in Not Submitted column if not proposed by applicant), with any proposed handicapped ramps at intersections
________   __________    14. Any proposed bicycle paths (place No in Not Submitted column if not proposed by applicant)
________   __________    15. Names of existing streets and proposed names of new streets
________   __________    16. Designation which streets are proposed to be dedicated to the township or to remain private
________   __________    17. Evidence that any proposed or higher category new street or driveway entrance onto a state road will meet PennDOT sight distance requirements, unless a highway occupancy permit has already been approved for the use
________   __________    18. Sight distance triangles meeting township requirements
         H. UTILITY PLAN:
________   __________    1. As applicable, the following existing and proposed items shall be shown for each lot, using standard symbols that are identified on a legend.
               a. Well (if not connected to central water system) - with required separation distance shown from septic drain fields, and with dimensions from lot lines
               b. Primary drain field (with dimensions from lot lines)
               c. Secondary drain field - shall be perc tested, and dimensioned from lot lines
               d. Suitable soil probe location
               e. Suitable percolation test locations (2 sites required meeting DEP requirements)
               f. Unsuitable percolation test location(s) - if any
            2. If on-lot sewage disposal service is proposed: (see also “supporting documentation” in division (O) below in this table)
________   __________       a. Proposed contour lines on same sheet as utility layout
________   __________       b. Location of existing and proposed wells within 100 feet of the boundaries of the project
________   __________       c. Proposed or typical location of dwelling/building
________   __________       d. Locations of soils with a seasonally high water table averaging less than 3 feet (see county soil survey)
________   __________       e. Exact slope across primary and secondary sewage system sites
            3. If public or central sewage service is proposed:
________   __________       a. Proposed contour lines on same sheet as utility layout
________   __________       b. Location and size of mains and laterals, with locations corresponding to stationing on the profile
________   __________       c. Locations of manholes, with invert elevation of flow line and grade at top of each manhole
________   __________       d. Proposed lot lines and any proposed easements or rights-of-way needed for the utilities
________   __________       e. Location of all other drainage facilities and public utilities in the vicinity of sanitary sewer lines
________   __________       f. Type, size, length and grade of sewer lines
            4. If public or central water service is proposed:
________   __________       a. Location and size of existing and proposed water mains
________   __________       b. Existing and proposed fire hydrant locations
________   __________       c. Distance noted that water lines will have to be extended to reach existing lines (if not already abutting the parcel)
________   __________    5. Any existing and proposed underground natural gas, electrical, telephone, cable TV or other utility lines, with any easements shown that will affect development
________   __________    6. List of contacts for all underground utilities in the area, with phone numbers stated on the grading plans (as required by State Act 172)
         I. GRADING AND STORMWATER MANAGEMENT PLAN: Note: § 154.007 may allow deferral of submission of engineering details until the final plan stage.
________   __________    1. Existing and proposed storm drainage facilities or structures, including detention basins (with capacity), swales, pipes (with sizes), culverts and inlets
________   __________    2. Capacity, depth, dimensions and locations of detention basins
________   __________    3. Pre-development and post-development watershed areas for each detention basin or major drainage channel or point of concentration
________   __________    4. Locations of any proposed or existing stormwater easements
________   __________    5. Intended design year standards for culverts, bridge structures and/or other stormwater facilities
________   __________    6. Schematic location of all underground utilities
________   __________    7. Entity responsible to maintain/own any detention basin and other stormwater facilities or conveyances
________   __________    8. Any additional information needed under the township stormwater management ordinance
________   __________    9. Existing and proposed contour lines (see description under natural features)
         J. FOR USES OTHER THAN SINGLE-FAMILY DETACHED OR TWO-FAMILY DWELLINGS:
________   __________    1. Evidence that the project meets the density requirements of the zoning ordinance, stating maximum and proposed densities
________   __________    2. Evidence that the project will meet the off-street parking requirements of the zoning ordinance, including existing, minimum and proposed numbers of spaces
________   __________    3. Arrangement of off-street parking spaces, parking aisles, off-street loading areas and extent of areas to be covered by gravel or asphalt
________   __________    4. For single-family attached dwellings, any proposed methods to ensure privacy between outdoor semi-private areas (such as fences or walls or plantings between rear yards)
________   __________    5. Illustrative sketches of exteriors of proposed buildings (encouraged but not required)
________   __________    6. Location of any proposed outdoor storage areas
________   __________    7. Note stating total square feet of paved area, including gravel areas
         K. EROSION AND SEDIMENTATION PLAN: (may be submitted at the final plan stage if the applicant provides a written and signed statement that earth will not be disturbed until after final plan approval)
________   __________    1. Drawings showing locations and types of proposed erosion and sedimentation control measures, complying with the regulations and standards of the Lehigh County Conservation District and DEP
________   __________    2. Narrative describing proposed soil erosion and sedimentation control methods
         L. ROAD PLAN-PROFILES: (with profile drawings on same sheet as plan drawings; unless waived under § 154.007(C))
________   __________    1. Profile of existing and proposed ground surface along centerline of street
________   __________    2. Proposed centerline grade with percent on tangents and elevations at 50 feet intervals
________   __________    3. All vertical curve data including length, elevations and minimum sight distance as required by §§ 154.160 through 154.179
________   __________    4. Cross-sections as required by the Township Engineer
         M. SANITARY SEWER AND STORM DRAIN PLAN-PROFILES: (with profile drawings on same sheet as plan drawings) (Unless waived under § 154.007(C))
________   __________    1. Profile of proposed ground surface with elevations at top of manholes or inlets
________   __________    2. Profiles of storm sewer and sanitary sewer lines, corresponding to stationing of any street
________   __________    3. All line crossings of other utilities
________   __________    4. Invert elevation and top of grate or manhole elevation
         N. CONSTRUCTION DETAILS:
________   __________    1. Detailed plan and cross-sectional drawings for detention or retention basins
         O. CONSTRUCTION DETAILS: (following any applicable township improvement standards).
________   __________    1. Typical cross-section and specifications for street construction as required by § 154.163
________   __________    2. Drainage swale cross-section and materials
________   __________    3. Pipe bedding details
________   __________    4. Storm drainage structures details, including cross-sectional drawings, any detention basin outfall structure and spillway
________   __________    5. Sanitary sewer structures
________   __________    6. Curb and sidewalk details
________   __________    7. Street tree details
________   __________    8. Erosion and sedimentation details
________   __________    9. Centralized water details
         P. SUPPORTING DOCUMENTS AND ADDITIONAL INFORMATION:
________   __________    1. Residual lands sketch: if the submitted plans do not include all undeveloped or underdeveloped adjacent or abutting lands owned by the same landowner or under control of the same developer, then a sketch shall be submitted at an appropriate approximate scale, on 1 sheet, covering all such land holdings together with a sketch of a reasonable future potential street system. Such sketch shall demonstrate that the proposed subdivision provides for the orderly development of any residual lands and/or does not adversely affect the potential development of residual lands
________   __________    2. Sewage planning: if a sewage facility planning module is required by DEP, then prior to preliminary plan approval, the applicant shall submit 2 complete copies for township use, plus the developer shall submit copies of the module and required accompanying plans to various agencies as required under state regulations. The approval of a sewage planning module is not required until final plan approval, but the applicant shall provide evidence that they are forwarding complete submittals to the proper review agencies
________   __________    3. Central water: if central water service is proposed by an existing water company or authority, the applicant shall provide a letter from such water company or authority which states that the company or authority expects to be able to adequately serve the development, that the proposed water system is acceptable
________   __________    4. Public sewage: if service is proposed by a public sewage provider, the developer shall submit a copy of a letter from the provider which states that the authority can adequately serve the subdivision, that the proposed sanitary sewage system is acceptable
________   __________    5. Nonpublic sewage: if service is proposed by a central sewage system that is not publicly-owned, the developer shall provide sufficient information to show that the proposed system would be feasible, within DEP regulations and maintained and operated through an acceptable system
________   __________    6. Access to state roads: if access is proposed to a state highway: a) copy of any information submitted to PennDOT and any correspondence from PennDOT regarding the proposed access to state roads (this requirement applies throughout the entire approval process); and b) evidence that the proposed access will meet PennDOT sight distance requirements
________   __________    7. Floodplain: if the project would include any area within the 100-year floodplain or any watercourse, a statement from the Zoning Officer indicating that the proposed subdivision or land development would be in compliance with the floodplain regulations of the township
________   __________    8. A statement describing the organization, major officers and principal shareholders of a corporate developer or the general partner of a partnership that is the applicant
________   __________    9. Method of ensuring maintenance of any private street
________   __________    10. List of any modifications or waivers requested to this chapter
________   __________    11. Copies of the decisions of any zoning variances, or special exception use approvals that are relevant to the proposal
________   __________    12. Stormwater calculations meeting the requirements of the township stormwater management ordinance
________   __________    13. For industrial operations or industrial storage: a written description of the proposed use in sufficient detail to indicate: a) any noise, glare, smoke and fumes nuisances; b) to allow a general determination of possible fire, explosive, toxic, genetic, public health or other hazards; and c) to estimate the amount, direction and times of any tractor-trailer truck traffic that is expected
________   __________    14. Traffic impact study if required under §§ 154.160 through 154.179
________   __________    15. Ground water study if required under §§ 154.160 through 154.179
________   __________    16. With each revision of a previously submitted plan, the plan preparer shall either:
               a. Certify in writing that no changes were made to the plan, other than changes requested by the township; or
               b. List the changes that were made, other than those changes requested by the township
 
(Ord. 127, passed 3-18-2010)