A. Following receipt of the Township Engineer's review of the stormwater management plan, the Board of Commissioners shall review and approve or disapprove a stormwater management plan submitted pursuant to § 206-44A.
B. The Township Engineer shall review and approve or disapprove a stormwater management plan submitted pursuant to § 206-44B and C.
C. The Township Engineer shall review all stormwater management plans for consistency with this chapter and any additional stormwater management provisions contained in the Township Code, as applicable, as well as accepted engineering practices.
D. No stormwater management plan for a regulated activity shall be approved if the stormwater management plan has been found to be inconsistent with this chapter as determined by the Township Engineer.
E. The developer shall be responsible for completing a certified as-built survey prepared by a professional land surveyor of all stormwater management facilities included in the approved stormwater management plan. Criteria for the as-built plan will be provided at the preconstruction meeting. The certified as-built survey and explanation of any discrepancies with the design plans shall be submitted to the Township Engineer for review and approval. In no case shall the Township Engineer approve the as-built survey until the Township Engineer receives a copy of an approved declaration of adequacy, highway occupancy permit from PennDOT and any applicable permits from DEP.
F. Modification of plans.
(1) A modification to a submitted stormwater management plan for a proposed development site which involves a change in control methods or techniques or which involves the relocation or redesign of control measures or which is necessary because soil or other conditions are not as stated on the stormwater management plan as determined by the Township Engineer shall require the resubmission of a modified stormwater management plan consistent with § 206-43 and subject to review per this chapter.
(2) Minor design changes may be permitted as authorized by the Board of Commissioners and as recommended by the Township Engineer without resubmission consistent with the requirements of this chapter.
(3) A modification to an approved stormwater management plan shall require a new stormwater management permit. The permit shall be issued following approval of the revised plan.
G. Resubmission of disapproved stormwater management plan. A disapproved stormwater management plan may be resubmitted, with the revisions addressing the Township Engineer's concerns documented in writing, to the Township Engineer in accordance with the plan submittal requirements of this chapter and subject to the plan review requirements of this chapter. The applicable Township Engineer's review security must accompany a resubmission of a disapproved stormwater management plan.