§ 206-44.   Plan submission.
   A.   For subdivision and land development:
      (1)   The stormwater management plan shall be submitted by the developer to the Office of Code Enforcement as part of the preliminary plan submission for a subdivision or land development.
      (2)   Eighteen copies of the stormwater management plan and any reports shall be submitted.
      (3)   Distribution of the stormwater management plan shall be as follows:
Distribution
Number of Copies
Distribution
Number of Copies
Township
1
Commissioners Planning Committee
7
Township Engineer
2
Township Manager
1
Township Solicitor
1
Code Enforcement Office
1
Planning Advisory Board
1
Environmental Protection Advisory Board
1
Public Works Department
1
Parks and Recreation Department
1
Montgomery County Planning Commission
1
 
      (4)   Developer is responsible for submitting plans and reports to Montgomery County Conservation District, Pennsylvania Department of Environmental Protection, Army Corps of Engineers, Montgomery County Planning Commission and other agencies as required for permitting.
   B.   For new or additional construction of impervious or semi-pervious surfaces, buildings or structures that do not require action by the Board of Commissioners under § 206-44A, six copies of the stormwater management plan shall be submitted by the developer to the Office of Code Enforcement as part of the building permit application. Distribution of the stormwater management plan and any reports shall be as follows:
 
Distribution
Number of Copies
Code Enforcement Office
1
Public Works Department
1
Township Engineer
2
 
   C.   For diversion or piping of stream channel and installation of stormwater systems:
      (1)   The stormwater management plan shall be submitted by the developer to the Office of Code Enforcement, the Montgomery County Planning Commission and the Montgomery County Conservation District for coordination with the DEP permit application process under chapter 105 (Dam Safety and Waterway management) or chapter 106 (Flood Plain Management) of DEP' s rules and regulations.
      (2)   Six copies of the stormwater management plan shall be submitted to the Office of Code Enforcement for distribution as follows:
 
Distribution
Number of Copies
Code Enforcement Office
1
Public Works Department
1
Township Engineer
2
 
   D.   The stormwater management plan shall be accompanied by the permit application and requisite permit fee, in accordance with the fee schedule adopted by the Board of Commissioners and found in chapter 110, Fees, of the Township Code.