§ 156.022 APPROVAL OF ZONING USE PERMIT.
   Within 45 days after the receipt of an application, the Building Inspector shall either approve or disapprove the application in conformance with the provisions of this chapter. All zoning use permits shall, however, be conditioned on the commencement of work within one year. One copy of the plans shall be returned to the applicant by the Building Inspector, after the Building Inspector shall have marked such copy either as approved or disapproved and attested to same by his signature on such copy. One copy of the plans, similarly marked, shall be retained by the Building Inspector. The Building Inspector shall issue a placard, to be posted on a conspicuous place on the property in question, attesting to the fact that the use or alteration is in conformance with the provisions of this chapter.
(Ord. 80-0-24, passed 1-12-81)