The developer shall be responsible for providing soils testing results to the City Engineer to verify compliance with compaction requirements listed in the IDOT Standard Specifications.
(A) In general, soils tests shall be taken every 200 feet, eight feet off of the centerline; at intersecting streets; and at sag (low) points.
(B) A written report from a registered professional engineer, certifying that soils throughout the embankment and subgrade material uniformly meet the compaction requirements, shall be provided to the city at least 24 hours prior to paving or pouring curb and gutter.