§ 152.49 SUMP PUMP DRAIN LINE SYSTEM.
   (A)   The subdivider shall provide sump pump drain lines to drain the sump pump discharge lines from each lot or parcel in the subdivision where a sump pump drain line cannot be discharged directly into a drainage ditch or swale. Sump pump drain lines are not required for lots one acre or greater and sump pump lines must discharge to the rear of all properties.
   (B)   Sump pump drain lines shall be installed in the grass area between the sidewalk and curb. The street storm sewer pipes shall not have tee connections installed for sump pump drain lines.
   (C)   Manholes or cleanouts shall be provided on the sump drain lines at a maximum spacing of 500 feet and shall be located in street right-of-way or easements adjacent to street right-of-way accessible for maintenance.
   (D)   Sump drain lines shall discharge into drainage ditches, storm sewer inlets or storm sewer manholes.
   (E)   A tee in the sump pump drain line shall be provide for each lot. The subdivider shall install a lateral line for each lot and install a cleanout at the property line. The owner of each lot shall install a lateral line between the house and the lateral cleanout connection.
   (F)   All sump drain line construction within the street right-of-way shall be in accordance with the village’s construction standards and shall become a part of the village’s storm sewer system. Outside the village’s corporate limits, sump pump drain lines shall be maintained by the property owner.
   (G)   All sump drain lines located below sidewalks, curb and gutters shall be backfilled with select granular backfill.
   (H)   All sump drain line trenches in or adjacent to street right-of-way shall be compacted by mechanical compaction to 95% SPD in minimum 12-inch loose lifts, or another means, as approved by the Village Engineer.
(Ord. 16-102, passed 4-4-2016)