10-18D-1: PERMIT REQUIRED:
When any blasting is to occur within the city, a permit for such activity shall be applied for at least three (3) working days prior to the desired blasting day. A detailed blast plan shall be submitted for review at the time of application for a permit. The blast plan shall contain the following information:
   A.   Number of holes per blast.
   B.   Blast pattern.
   C.   Depth of holes.
   D.   Maximum holes per delay.
   E.   Number of delays used.
   F.   Type of explosive used.
   G.   Total pounds of explosive.
   H.   Method of detonation.
   I.   Proximity to nearest structure.
   J.   Expected duration of blast activity.
   K.   Name of independent monitoring company. (Ord. 2012.04, 1-18-2012)
   L.   Outline for notification of the Hurricane Valley fire district one hour in advance of each blast and approximate time of each blast. (Ord. 2012.04, 1-18-2012; amd. 2014 Code)