§ 153.150 DEVIATIONS OCCASIONED BY STRUCTURES OR UTILITIES.
   Wherever obstructions are encountered during the progress of the work and interfere to such an extent that an alteration in the work is required, the developer’s engineer shall have the authority to change the drawings and order a deviation from the line and grade or arrange with the owners of the structures for the removal, relocation, or reconstruction of the obstructions. Where gas, water, telephone, electrical, hot water, steam, or other existing utilities are an impediment to the vertical or horizontal alignment of a new pipeline, the developer’s engineer shall order a change in grade or alignment or shall direct the subdivider to arrange with the owners of the utilities for their removal.
(Ord. 97-7, passed 7-1-1997, § 5.16)