The City may charge an additional amount under the following circumstances providing that an area of benefit or benefiting properties are identified along with the capital improvement cost:
(a) Where a specific wastewater pipeline project benefits an identifiable area by providing needed capacity or correcting a substandard condition.
(b) Where the costs associated with a specific City improvement project such as a major pipeline project exceed that which normally could be collected via the wastewater connection charge.
(c) Where the city has entered into a reimbursement agreement with a developer or landowner for a capital improvement project installed by the latter.
(Ord. 1515-NS, eff. June 5, 2009)