City Council acceptance of wastewater facilities shall only follow completion of the physical improvements as well as administrative items as required by the Wastewater Design and Construction Standards, Municipal Code, or as deemed necessary by the Public Works Director. Acceptance of wastewater facilities may be delayed until substantial use is either present or anticipated as evidenced by the construction of buildings/houses and occupancy of those units. Acceptance may be delayed until at least seventy-five (75%) percent of the buildings/houses are under construction or at least fifty (50%) percent of the buildings/houses are occupied.
(Ord. 1515-NS, eff. June 5, 2009)