Where it is in the interest of the petitioner to complete construction of the improvements, required by the primary approval, in phases rather than all at once, the petitioner shall so state in writing to the Plan Commission, along with the petition for secondary approval, and deliver the request together with maps and drawings showing the intended phasing of the project. The Plan Commission may at its option provide secondary approval to each phase as it is built, provided that at no time shall the phasing plan produce an unsafe condition or a utility plan that is not in compliance with the requirements of the primary approval, of Indiana law or this chapter. A phasing plan shall not produce additional cost to any utility over and above the cost that would be incurred if the overall plan was developed at one time.
(Ord. 970, passed 3-5-2007)