§ 152.046 DESCRIPTION AND SPECIAL REQUIREMENTS OF IDENTIFIED FLOODPLAIN AREAS.
   The identified floodplain area shall consist of the following specific areas.
   (A)   The Floodway Area/District identified as floodway in the FIS which represents the channel of a watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation by more than one foot at any point. This term shall also include floodway areas which have been identified in other available studies or sources of information for those special flood hazard areas where no floodway has been identified in the FIS.
      (1)   Within any floodway area, encroachments, including fill, new construction, substantial improvements or other development shall not be permitted unless it has been demonstrated through hydrologic and hydraulic analysis performed in accordance with standard engineering practice that the proposed encroachment would not result in any increase in flood levels within the community during the occurrence of the base flood discharge.
      (2)   No new construction or development shall be allowed, unless a permit is obtained from the Department of Environmental Protection Regional Office.
   (B)   The AE Area/District shall be those areas identified as an AE Zone on the FIRM included in the FIS prepared by FEMA for which base flood elevations have been provided.
      (1)   The AE Area adjacent to the floodway shall be those areas identified as an AE Zone on the FIRM included in the FIS prepared by FEMA for which base flood elevations have been provided and a floodway has been delineated.
      (2)   AE Area without floodway shall be those areas identified as an AE zone on the FIRM included in the FIS prepared by FEMA for which base flood elevations have been provided but no floodway has been determined.
         (a)   No permit shall be granted for any construction, development, use or activity within any AE Area/District without floodway unless it is demonstrated that the cumulative effect of the proposed development would not, together with all other existing and anticipated development, increase the BFE more than one foot at any point.
         (b)   No new construction or development shall be located within the area measured 50 feet landward from the top-of-bank of any watercourse, unless the appropriate permit is obtained from the Department of Environmental Protection Regional Office.
   (C)   (1)   The A Area/District shall be those areas identified as an A Zone on the FIRM included in the FIS prepared by FEMA and for which no 1% annual chance flood elevations have been provided. For these areas, elevation and floodway information from other federal, state or other acceptable sources shall be used when available. Where other acceptable information is not available, the base flood elevation shall be determined by using the elevation of a point on the boundary of the identified floodplain area which is nearest the construction site.
      (2)   In lieu of the above, the municipality may require the applicant to determine the elevation with hydrologic and hydraulic engineering techniques. Hydrologic and hydraulic analyses shall be undertaken only by professional engineers or others of demonstrated qualifications, who shall certify that the technical methods used correctly reflect currently accepted technical concepts. Studies, analyses, computations and the like, shall be submitted in sufficient detail to allow a thorough technical review by the municipality.
   (D)   Community identified flood hazard areas shall be those areas where the borough has identified local flood hazard or ponding areas, as delineated and adopted on a local flood hazard map using best available topographic data and locally derived information such as flood of record, historic high water marks, soils or approximate study methodologies.
(Ord. 262-2014, passed 3-10-2014)