§ 150.39 INSPECTIONS.
   (A)   Inspections by the borough may be carried out on a random basis at the option of the borough.
   (B)   A final inspection shall, at the option of the borough, be conducted by the borough to verify compliance with this subchapter.
   (C)   In all cases, however, the permittee shall be required to undertake all earthmoving and grading activities in accordance with this subchapter and the approved site improvement and grading plan, whether or not inspection by the borough is provided. As-built plans shall be required prior to the issuance of a certificate of occupancy if the owner or permittee is seeking any change to the approved site improvement and grading plan.
   (D)   The Borough Council shall appoint the person(s) responsible for enforcement and field inspection associated with this subchapter.
   (E)   When weather conditions or time of year prevent the permittee from completing all earth moving and grading activities prior to a request for an occupancy permit, the borough, on a case by case basis, may issue a temporary occupancy permit upon satisfaction of all of the following criteria:
      (1)   All final earth moving and soil stabilization that can be completed is completed;
      (2)   Temporary soil erosion and sedimentation control facilities properly installed and in good repair;
      (3)   Temporary seeding and mulching of disturbed areas is complete; and
      (4)   The owner provides an agreement to the satisfaction of the Borough Solicitor to guarantee completion of the earth disturbance within six months of the date of the agreement.
(Ord. 218-2006, passed 6-5-2006)