905.05 RESTORATION OF PAVEMENT.
   (a)    The restoration of pavement or other surface shall be performed under the direction and to the satisfaction of the Service Director.
   (b)    The backfilling over the drains, sewers or other utility lines, after they have been laid and accepted by the proper official, shall be done with granular material and tamped to the top of the pavement. All backfill and bedding shall be performed as directed by the Service Director. All paving which is removed must be replaced within forty-eight hours after the completion of the work in the excavation, unless instructed by the Service Director. The restoration shall be done so as to make the pavement at least as good as it was before it was disturbed. The contractor shall be responsible for any subsequent settlement of the ground or pavement. All other utility lines must be protected from settlement or injury. All utilities whose lines are encountered shall be immediately contacted by the contractor.
   (c)    Upon failure or refusal of the permittee satisfactorily to fill the excavations, restore the surface and remove all excess materials within the time specified in the permit, or, where not specified therein, within a reasonable time after commencement of the work, the Service Director shall have it done and the cost thereof shall be deducted from the deposit posted as provided in Section 905.01. If the cost of such restoration exceeds the amount of such deposit, the proper officer of the City shall proceed to collect the remainder due from such permittee, and no permit shall be subsequently granted until such amounts are paid.
(Ord. 35-69. Passed 8-4-69.)