1305.19 COMMENCEMENT WORK; TIME EXTENSIONS.
   If construction, erection, alteration, or other work upon the building has not commenced within twelve (12) months of the approval of the plans or drawings and specifications, the owner may request an extension. One extension shall be granted for an additional twelve (12) month period if requested by the owner at least ten (10) days in advance of the expiration of the permit and upon payment of a fee not to exceed one hundred dollars ($100.00). Additional extensions of six (6) months each may be granted by the Chief Building Official upon the showing of good cause by the owner. Before any extension is granted, the owner of the building shall resubmit the plans or drawings and specifications for approval pursuant to this section.
(Ord. 2007-501. Adopted 10-15-07.)