1305.17 APPROVAL IN PART.
   (a)    The Building Official may issue a permit for the construction of footings and foundations or any other part of building or structure before the complete drawings and specifications for the whole building have been submitted. Adequate information and detailed statements shall be filed to demonstrate that an unjustifiable hardship will be entailed by the applicant if he is required to delay initiation of such work until completion and approval of the drawings and specifications, together with such other data as may be necessary to demonstrate that the work will comply with all the pertinent requirements of this Building Code.
   (b)    The holder of such permit for the foundation or other part of the building or structure shall proceed at his own risk with the building operation and without assurance that a permit for the entire structure will be granted.
   (c)    In addition to drawings depicting the work to be done, site plans are required to be submitted in duplicate.
   (d)    A separate fee shall be assessed for the partial approval. This is in addition to the fee for the entire project.
(Ord. 2007-501. Adopted 10-15-07.)