943.12 MAINTENANCE AND FINAL INSPECTION APPROVAL.
   To receive final inspection and acceptance of any project, or portion thereof, the following must be completed and provided to the County Drainage Engineer:
   (a)   Final stabilization must be achieved and all permanent storm water management and post construction water quality practices must be installed and made functional, as determined by the County Drainage Engineer and per the approved Comprehensive Storm Water Management Plan.
   (b)   An As-Built Certificate, including an As-Built Survey and Inspection Report, sealed, signed and dated by a Professional Engineer and a Professional Surveyor with a statement certifying that the storm water management and water quality practices, as designed and installed, meet the requirements of the Comprehensive Storm Water Management Plan approved by the County Drainage Engineer. In evaluating this Certificate, the County Drainage Engineer may require the submission of a new set of storm water practice calculations if he/she determines that the design was altered significantly from the approved Comprehensive Storm Water Management Plan.
   (c)   A copy of the complete and recorded Inspection and Maintenance Agreement, which will include the entity responsible for long-term maintenance, as specified in Section 943.08.
(Ord. 2013-364. Adopted 8-26-13.)