§ 154.030 USE OF PUBLIC ROADS.
   (A)   The applicant shall identify all state and local public roads to be used within the city to transport equipment and parts for construction, operation, or maintenance of the commercial wind generator facility.
   (B)   The city’s Public Works Superintendent or a qualified third party engineer hired by city shall document road conditions prior to construction. The Public Works Superintendent or a third party engineer shall document road conditions again 30 days after construction is complete or as weather permits.
   (C)   The city may require that the road(s) to be used be bonded by the applicant.
   (D)   Any road damage caused by the applicant or its contractors shall be promptly repaired at the applicant’s expense and repairs must be approved by Public Works Superintendent.
   (E)   The applicant shall demonstrate that it has appropriate financial assurance to ensure the prompt repair of damaged roads either through a bond or a irrevocable letter of credit.
(Ord. 19, passed - -2008)