(A) Governing standards. Should the requirements of this chapter not cover the specific variables of a given installation, the latest edition of the State Public Works Standard Specifications shall govern.
(B) Pipelines.
(1) Installation of underground pipelines shall be per the specific manufacturer’s recommendations, OSHA requirements, and in accordance with the figure in § 9-3-8, when open trenching is allowed.
(2) All pipelines shall be bored and cased under existing paved streets, unless permission to open cut is given by the town Mayor. Bore casing ends shall be plugged with grout.
(Prior Code, § 9-3-3)
Where the town Mayor has given permission for open cut utility installations in existing paved streets or a paved street requires repair, the following minimum standards shall apply for pavement repair.
(A) Subgrade shall be compacted to 95% standard proctor density at within 5% optimum moisture.
(B) Adjacent concrete pavement shall be saw cut a depth of two inches true to line, squared, and removed with a jackhammer.
(C) Adjacent asphalt pavement shall be saw cut or jackhammered within an asphalt chisel true to line, squared, and removed with a jackhammer.
(D) Subgrade shall be uniform depth from edge to edge.
(E) Concrete thickness, compressive strength, finish, jointing, and curing shall be per figure in § 9-3-8.
(Prior Code, § 9-3-4)
Town employees are hereby authorized to perform all work required under the terms of this chapter, but such work shall be at the discretion of the Town Maintenance Department and shall not interfere with other duties. In the event town employees perform such services, the landowner for whose benefit the work is performed shall pay to the town an hourly charge for its employees, determined by the town, such equipment charges as the town may impose, and all material and other costs to the town.
(Prior Code, § 9-3-5)